Azure Devops picking the "wrong" sprint to show in Sprint board
02:19 19 Jun 2025

I have an issue with Azure Devops.

We've fairly recently switched to using SAFe (Scaled Agile Framework for Enterprises), and so now we're doing all our planning in 3-month increments, with 6 iterations of 2 weeks each in each increment.

This now means our project structure in terms of iterations is hierarchical, and looks something like this:

Iteration      Runs from/to
-------------------------------
PI 5           May 5 - Jul 25
    IT 5.1     May 5 - May 16
    IT 5.2     May 19 - May 30
    IT 5.3     Jun 2 - Jun 13
    IT 5.4     Jun 16 - Jun 27
    IT 5.5     Jun 30 - Jul 11
    IT 5.6     Jul 14 - Jul 25
    

The problem arises when trying to show the Sprint overview in Azure Devops. Earlier, when we had a "flat" list of our sprints / iterations, Azure Devops would also jump to the "correct" sprint as the "current" sprint and display it - based on the "from" and "to" dates of that sprint.

Now, with this hierarchical setup, unfortunately, Azure Devops always just jumps to "PI 5" - the whole 3-month increment - but it doesn't actually jump to the correct current sprint, which would be "IT 5.4" (Jun 16-30).

Is there any way we can tell Azure Devops to ignore the top-level PI entries, and just find the correct sprint in the list of "child iterations" for a PI entry?

As requested by @khalito, this is a screenshot of Team configuration > Iterations - this list is being generated when a new PI cycle is created in the "parent" project, and assigned to my team:

enter image description here

I have not found any way to reorder this list that mixes the whole "PI" cycle, and the iterations inside that PI.

azure-devops azure-boards sprint